Incident Action Plan Preparation - Work Period
Coordinator
Participants
Section Chiefs
Purpose
- Appropriate IMT members must immediately complete the assigned task/products that are needed for inclusion in, and/or approval of, the IAP. These products must meet the deadline set by the PSC so that Planning can assemble the IAP components.
- The deadline must be early enough to permit timely Incident Commander/ Unified Command (IC/UC) review, approval, and duplication of sufficient copies for the Operations Briefing and other IMT members.
When
After the Planning Meeting
Duration
Approximately 2 hours
Critical Work Activities
- Ensure IAP and supporting plans are finalized and incorporate any changes identified in the Planning Meeting.
- Set time to meet with IC/UC to review changes to IAP and gain approval of IAP (with IC/UC signatures) for Operations Briefing.
- Make appropriate number of copies of IAP for Operations Briefing.
- Utilize IAP Approval Checklist in Section 9.
Tactics, Meeting, Prep for, Planning, Planning, Meeting, Prep for Tactics, Operational, Period, IAP Prep &, Approval, Command &, General Staff, Briefing/Mtg, Understanding, the Situation, (ongoing), Operations, Briefing, Command, Objectives, Meeting, Implement New IAP & Assess, Progress
Typical IAP Components
Incident Management - Detailed Incident Action Plan (IAP) As appropriate